Al Merjal is the first Iraqi company completion for full Rehabilitation for Thermal Power Plant
Rehabilitation Of 2 Units Of 220 Mw Each, For Baiji Thermal Power As Subcontractor For ANSALDO Energy, Italy, In 1999 To 2000 . Work Includes Boilers, Turbines, Generators, And B.O.P. Mechanical, Electrical, I&C , Inspection, Pre Commissioning & Commissioning.
Al Merjal is the first Iraqi company completion for full construction gas turbine plant; Complete Construction Of two Unit 265 MW (V.94.3) & 60 MW (V.64) Gas Turbine For TAZA Power Plant, 2004-2005, with SEIMENS as turnkey job ,Starting From Site preparation , Foundation, Steel Structures, GT, Air Intake, Auxiliary, Balance Of Plant, Piping And Fitting, Buildings, Gas Reduction Station, Water Treatment Unit, Fire Fighting Network , Control. Switch.
Rehabilitation of Unit 1,2,3,4 and 6 capacity 220 MW each, for Baiji Thermal Power Plant with Bechtel Co.,in 2004 to 2005 . Work includes boilers, turbines , generators, and B.O.P. Mechanical , electrical , I&C , Inspection, Pre commissioning & commissioning.
Rehabilitation of 2 boilers (580 Ton/Hr.) for units 5&6 including mechanical , electrical , I & C inspection , pre commissioning and commissioning with BABCOCK Co. , project started 2002, and finished in 2003.
Construction unit (3 &4 ) Baiji Gas Turbines (V.94.2) 159 MW each, with Odabrecht Co. 2005-2006. Complete Construction Of two Unit 159 MW (V.94.2) Gas Turbine For beiji Power Plant, as turnkey job ,Starting From Site preparation , Foundation, Steel Structures, GT, Air Intake, Auxiliary, Balance Of Plant, Piping And Fitting, Water Treatment Unit, Fire Fighting Network , Control. Switch Gear And I&C
Engineering , Supply & Construction of new, 150 ton/ hr, Bono Made for Daura oil refinery, ministry of oil .The scope of work included foundation, steel structure, and boiler installation. Pre-commissioning and commissioning, start up test for 72 hours, and over to client.
Installation of 2 fuel CU.M storage tanks for baiji plant includes foundation civil works
Complete Civil construction for Erbil gas power plant, 6X 125MW for ABB and private investor in Erbil city.
Completed in 2009
Installation of complete fire fighting network for Seeneya Refinery 20,000 brl/day/North Refinery Co. NRC, 2005.
Work included Piping, Feed Pump, Electronics including Alarm and Detection Instrumentation, Wiring, Control Panels.
LIST OF ALL PAST PROJECTS
Rehabilitation of unit 3 turbine and generator in MUSSAIB thermal power plant
Siemens - 2018-2019
Assessment and logistic services for AL-MUSSAIB TPS with GE preparing for rehabilitation of units 1,2 & 4.
General Electric Service Global - 2016-2017
Construction work for HFO deseil power plant with capacity of 4x6 MW
Wartsila - 2015
Rehabilitation of chemical
separation tower type O6 H1B
Aradat - 2014
EPC steam boiler 150 ton/hr of Bono made for DURA Refinery
BONO ENERGIA - 2010-2013
Full replacement service work of circulating
water system of water intake , baiji TPS
The Iraqi Ministry of Electricity - 2011
Full replacement works of two lifting pumps
station with capacity of 33000 m3 /hr
The Iraqi Ministry of Electricity - 2010
Condenser Re-tubing Services of Thermal
Units no. 1 to 6 Baiji Thermal Power Plant
The Iraqi Ministry of Electricity - 2008-2009
Complete civi l Construction services of Erbil gas turbine power plant with capacity of (6 X 125MW )
ABB 2007-2008
Full site technical assessment
services of uni t 1 & 3 Hi tachi Boilers for JICA –Al- Mussaib Power Plant
HITACHI - 2007-2008
Erection and construction of one new boiler of 150 ton/hr of bono enerigia made in DURAH REFINERY
Bono Energia - 2005-2006
EPC firefighting system in Seneya Refinery
The Iraqi Ministry of Oil - 2006
Complete erection and construction of two units of SIEMENS made SGT4000 and SGT800 and of 265 MW and 65 MW respectively, including all civil and electro-mechanical works
Siemens Westinghouse - 2004-2005
Rehabilitation of 5 thermal units no. 1,2,3, 4 & 6 ( 220 M W capacity each) Baiji Thermal Power Plant
Bechtel company 2004-2006
Full Contraction of 8 gas turbine units manufactured by GE 25 M W capacity
Washington Group
(GE Supervision) 2004-2005
Installation of 2 L FO storage tanks 5000 m3 capacity BAIJI GPS.
The Iraqi Ministry of Electricity 2003-2004
Rehabilitation of unit 5 & 6 boilers 580 Ton/Hr. capacity each as well as allrelated auxiliary work Dora TPS
Babcock 2002-2004
A complete installation facility of 2 gas
turbine units no. 3 & 4 manufactured by
Siemens 159 MW capacity type V.94.2
ODEBRECHT Company
(Siemens Supervision) - 2004-2005
Dismantling of one complete Boiler 90
Ton/Hr. capacity and install new Boiler
capacity 160 Ton/Hr., Dora Refinery
The Iraqi Ministry of Oil - 2002-2003
Rehabilitation of 6 Boilers capacity 80 Ton/
Hr. Al-Phosphate chemical plant facility in
Al – Anbar Gov.
The Iraqi Ministry of Industry - 2001-2003
Rehabilitation of steam boiler with capacity of 80 Ton /Hr. Al-Phosphate chemical plant facility in Al – Anbar Gov
The Iraqi Ministry of Industry - 2000
Rehabilitation of 2 thermal power units 220MW capacity each
Ansaldo Energia - 1996-1998
Full replacement work services of water tube boiler and furnace as well for steam
boiler no. 1 to 4 Baji thermal power plant
The Iraqi Ministry of Electricity - 1996-1998